WSSC Broad Creek Project Completion: Summer 2020

(Click on the image for the October 2016 Newsletter)
The Broad Creek Waste Water Pumping Station (WWPS) was built in 1968
Consent Order - December 2005
3 remaining projects:
  • Beginning at Swan Creek Road along MD 210 going south to the Piscataway Waste Water Treatment Plant: projected substantial completion date is May 30, 2017.
  • Beginning at Swan Creek Road along MD 210 going north, turning left on Cornett Street and right on Livingston Road and ending  just before the intersection of Fort Washington Road and Livingston Road:  projected substantial completion is May 30, 2017.
  • Broad Creek WWPS Rehabilitation and Tunnel: anticipated substantial completion is Summer 2020 (based on early 2017 contracts award).